| Disco | Region | District | Substation | Type | Planned start | Planned completion | Actual completion | Responsible officer | Officer contact | Status | Percent complete |
|---|---|---|---|---|---|---|---|---|---|---|---|
|
NEDCo
|
Bono East
|
Jema
|
Cerehin road
|
Transformer Injection
|
Apr 20, 2026
|
Apr 24, 2026
|
|
Area Manager
|
|
Energized
|
95
|
|
NEDCo
|
Bono East
|
Atebubu
|
Adom road
|
Transformer Injection
|
Apr 20, 2026
|
Apr 24, 2026
|
|
Area Manager
|
|
Energized
|
95
|
|
NEDCo
|
Bono East
|
Atebubu
|
Prang yam market
|
Transformer Injection
|
Apr 20, 2026
|
Apr 24, 2026
|
|
Area Manager
|
|
Energized
|
95
|
|
NEDCo
|
Bono East
|
Nkoranza
|
Nation
|
Transformer Injection
|
Apr 20, 2026
|
Apr 24, 2026
|
|
Area Manager
|
|
Energized
|
95
|
|
NEDCo
|
Bono East
|
Bamboi
|
Banda Nkwanta moshie
|
Transformer Injection
|
Apr 20, 2026
|
Apr 24, 2026
|
|
Area Manager
|
|
Energized
|
95
|
|
NEDCo
|
Bono East
|
Nkoranza
|
Busunya Timeabu
|
Transformer Injection
|
Apr 20, 2026
|
Apr 24, 2026
|
|
Area Manager
|
|
Not Energized
|
80
|
|
NEDCo
|
Bono East
|
Bamboi
|
Banda Nkwanta EA Primary school
|
Transformer Upgrade
|
Apr 20, 2026
|
Apr 24, 2026
|
Apr 24, 2026
|
Area Manager
|
|
Loaded/Completed
|
100
|
|
NEDCo
|
Bono East
|
Kintampo
|
Blood of Jesus
|
Transformer Replacement
|
Apr 20, 2026
|
Apr 24, 2026
|
Apr 24, 2026
|
Area Manager
|
|
Loaded/Completed
|
100
|
|
NEDCo
|
Bono East
|
Kintampo
|
House of Power
|
Transformer Replacement
|
Apr 20, 2026
|
Apr 24, 2026
|
Apr 24, 2026
|
Area Manager
|
|
Loaded/Completed
|
100
|
|
NEDCo
|
Bono East
|
Atebubu
|
Amantin Asempanaye
|
Transformer Replacement
|
Apr 20, 2026
|
Apr 24, 2026
|
Apr 24, 2026
|
Area Manager
|
|
Loaded/Completed
|
100
|